Can a Granite Order Ship in Two Batches? Split the Shipment, Not the Production
Yes, you can ship in two batches, as long as the whole order is cut once and only leaves in two sailings. Cut 500 ㎡ as one full container plus one LCL booking and only 12.5 chargeable tonnes go by LCL; cut it at half and both batches fall into per-tonne billing, 28 tonnes more. The real risk is not freight, it is the second batch coming from different blocks.
Can a granite order ship in two batches?
Yes, but separate two things first: a split shipment and a split production run. In a split shipment every block for the order is reserved up front and the order is cut in one run; slab numbers run continuously from the first piece to the last, and the goods simply leave on two sailings. In split production each batch is reserved and cut on its own, the second batch comes from different blocks, and the colour will not match. That second version is what buyers usually mean, and the answer is no. So the accurate reply is: split the shipment, never the production. The test takes one question to the supplier: does the second batch's slab numbering carry on from where the first stopped?
Where does the extra money go when the order ships in two lots?
It goes to whichever lot cannot fill a container. A 20ft container takes 346 ㎡ of 30mm slabs, about 28 tonnes (346 × 0.081), and weight is what caps that figure, not volume, so anything short of a full container usually has to move as LCL and is charged by weight. Take 500 ㎡ and put three ways of sending it side by side, as in the table below, with two notes first. The 250 + 250 row compares two LCL bookings, while a 250 ㎡ lot can also take one 20ft container loaded to about seventy percent and pay the full container rate, and which is cheaper — the container rate or LCL — needs two quotes from your forwarder. Row one and row three share the same container type and sit in the same per-tonne band, and the ocean freight itself is the same; the difference is arrival timing, inspection count — inspected once, or twice with each lot sealed separately — and the second document set plus second customs declaration that row three carries. Those fixed charges are counted in the next section, so do not leave them out of the quote.
| Option | Containers and bookings | Square metres billed by weight | Chargeable tonnes |
|---|---|---|---|
| All 500 ㎡ in one go | 1 × 20ft FCL (346 ㎡) + 1 LCL booking (154 ㎡) | 154 ㎡ | 12.5 |
| Two lots, 250 + 250 | Two LCL bookings, no FCL | 500 ㎡ | 40.5 |
| Two lots, 346 + 154 | 1 × 20ft FCL + 1 LCL booking | 154 ㎡ | 12.5 |
Why can't the cut fall at half?
At half, neither lot fills a container: send both as LCL and all 500 ㎡ drops into weight-based billing (250 × 0.081 = 20.25 a lot, 40.5 for the two); book a 20ft box for each at seventy percent load and you pay two full container rates. Either way costs more than row one above — the only question is whether you pay by the tonne or by the box. Cut at a full container instead and only 154 ㎡ goes LCL, 12.5 chargeable tonnes, 4.62 m³ by volume (154 × 0.03), and the carrier bills on W/M, so weight still wins. The gap is 28 chargeable tonnes (40.5 − 12.5), and that covers the per-tonne leg only: the second booking, the second customs declaration and destination CFS handling are fixed charges on top and are not in this figure, so ask for them separately. One lower bound still applies: keep each lot above the 100 ㎡ minimum order, or you end up dearer than paying for a half-empty container.
How do I keep the second batch the same colour as the first?
There is exactly one mechanism: reserve every block for the order in one go, number the blocks in sequence, cut every slab of the order and give the whole run one continuous numbering, then draw the second batch out of those same numbers. Maple Red G562, a red-family granite, is where a second cutting run shows worst: split the base tone across two batches and the paving reads as a visible line where they meet. In our plant one order is scheduled once and cut through in a single pass, numbered from 1 to the end, and the second batch is pulled by number. Three things make it enforceable: state in the contract that both lots come from the same blocks; keep two sealed samples, one held by each side; print the batch number on every crate. On sawn surfaces nothing is polished away, so base tone and veining sit right on the face, and a slight shift between batches shows up more clearly once the stone is laid than it would on a polished face — which is why sawn material needs those three points most. How colour difference itself is inspected is covered in a separate guide.
Do I need two sets of documents or one?
Two lots means two bookings and two bills of lading. There is no shortcut where one bill of lading covers two ports of discharge, unless both the contract and the carrier agree to it in writing, so do not build the deal on that idea. Invoice and packing list come as one set per lot, and the two sets must add up to the contract value; the certificate of origin and the fumigation certificate for wooden packing are issued per lot, because the first lot's certificate does not cover the second lot's crates; customs declaration is filed per lot as well. The place this most often fails is the letter of credit: it must state that partial shipment is allowed, otherwise the bank pays once against one set of documents and the second lot's payment stalls on a discrepancy. Put simply, the batch on paper is a legal unit, not a logistics unit.
Which batch should ship first?
Ship the main field first and the specials second. The first lot carries the face course and the main paving; the second carries the edge trims and specials, which are set aside and numbered separately in the same cutting run according to the layout plan, and are never re-cut out of the first lot's slabs. The reason is sequence: the site lays the main field first, and edge pieces can only be measured once the field reaches the edge; send the specials first and the site stands idle until the field lands. The bonus is that laying starts as soon as the first lot arrives, and the second lot's trims drop in by number with no site cutting.
If we split, which four sentences belong in the contract?
Four sentences you can copy across. One: shipment in two lots is allowed, each lot with a stated date, never "as soon as possible". Two: the whole order is reserved once, blocks are numbered in sequence, and the second lot is drawn from those same blocks. Three: each lot carries its own document set and is settled per lot, with the balance due after the last lot is inspected. Four: each lot is inspected on its own, sealed samples are taken per lot, and each side keeps one. Each sentence covers one link — the calendar, the colour, the money, the disputes — and whichever is missing leaves that link with nothing to stand on.