Granite Kerbstone Embedment Depth: Measure the Exposed Height on the Correct Side First
Granite kerbstone embedment depth is a remainder, not a number you pick: section height minus road-side exposed height minus the mortar bed. A 300 high section with 150 exposed and a 20 mm bed leaves 130. The exposed height is the difference between two finished levels on the drawing, so say which side you measure.
How deep should a granite kerbstone be buried? First decide which side you measure
Embedment depth is a remainder, not a depth you choose on its own. Take the cross-section height, subtract the exposed height on the carriageway side, then subtract the mortar bed. What is left is the embedment. The exposed height is not one figure. On the carriageway side it equals the top level minus the finished carriageway level. Take both levels from the drawing; do not derive the exposure from the footway build-up, because the two agree only where the footway is built up from the carriageway surface. With the top flush, the footway side shows nothing, and the build-up tells you how much of that face is covered, not how high the carriageway side stands. The footway side shows exactly as much as the top rises above the paving, and that amount is not deducted a second time, because it already sits inside the top level. So “120 exposed” is not enough: say which side, and whether the top is flush with the footway or stands above it. Skip that and the section is sized off 120 alone, and on site the footway side may not be exposed at all.
Why is the exposed height not yours to set, but a subtraction of two levels on the drawing?
Because someone else fixes it first and you only divide what is left. Take a footway built up from the carriageway surface: a 30 mm slab, 20 mm mortar and 100 mm base give 150 mm, and the drawing shows the two finished levels 150 apart. With the top flush, the carriageway side is exposed 150, and a 300 high section with a 20 mm bed keeps 130 of embedment. Raise the top 20 mm above the footway and the exposed height becomes 170, so the same 300 section keeps only 110. Neither figure is yours to set; both come out of subtracting the two levels on the drawing. The cross-section height is the part you buy, and exposure and embedment are two shares of it: more exposure means less embedment and less depth biting into the base, so frost heave and settlement show up here first; more embedment means less exposure and a line that no longer holds water back. What stops a wheel pushing the kerb over is the restraint behind it, which the third limit below deals with.
How do you work back from the cross-section height?
One formula: embedment equals section height minus road-side exposed height minus the mortar bed. The table below lists three sections at 120 exposed and a 20 mm bed, and the 100×300 row also carries the weight calculation: 0.1 × 0.3 × 1 = 0.03 m³, times 2.7 t/m³, gives 81 kg per metre. Read the 100×200 row carefully: at 120 exposed only 60 mm is left below, which will not hold, so it belongs at a green edge or the inner side of a footway, not on a carriageway edge. A 150×300 at 2 m weighs 243 kg and needs lifting gear, not two men. This table holds at 120 exposed. The 300 section in section 2 is at 150 exposed, and the same row at that exposure is 130, not the 160 shown here. Change the exposure and the embedment changes with it, so recalculate from the two levels on the drawing.
| Section W×H (mm) | Embedment at 120 exposed, 20 bed (mm) | Weight per metre (kg) | One 2 m piece (kg) |
|---|---|---|---|
| 100×200 | 60 | 54 | 108 |
| 100×300 (example) | 160 | 81 | 162 |
| 150×300 | 160 | 121.5 | 243 |
What sets the lower limit on embedment?
Three limits sit side by side; the strictest governs and they are not added together. First, sit on something solid: the underside has to bear on the compacted base or on concrete, and the mortar bed only takes up tolerances. On backfill it follows the fill down however deep it goes. Second, frost: in cold regions embedment plus the mortar bed must exceed the local frost depth, and that depth comes from the local meteorological or design authority, not from a stone factory. If you cannot reach it, backfill behind the kerb and under the base with a material that does not heave, and give the water a way out. Third, something has to push back: where one side is open, as at a tree pit, a drain channel or a sunken planting bed, even a deep kerb rotates about its base, so add a concrete backing. All three have to hold: the solid base guards against settling, the frost limit against heave, and the backing against leaning. Creeping is outside all three — it comes from ends that are not locked and joints left open, and no depth prevents it.
The depth is right, so why does the kerb still lean?
Because there are three ways to go wrong and none of them is about depth. Leaning forward means nothing holds the back, so a wheel pushes the top over. Settling means the stone sits on backfill, and the fill compacts away under it, so the top line steps down run by run. Creeping means the ends are not tight and the joints are not dealt with, so one stone pushed along takes a row with it. None of these is a shortage of section height: going from 300 to 400 only takes the embedment from 130 to 230 and leaves the cause in place, so the money goes into stone. This article is about a kerb buried in the road structure to resist push and settlement; standing a stone up to retain soil belongs to flower-bed retaining walls, which are walls rather than kerbs.
How do you inspect embedment before backfill?
Put three numbers on the fabrication order and on the site instruction: section height, road-side exposed height, mortar bed thickness. With those three the embedment is arithmetic, not a site measurement. Before backfill, transfer the finished carriageway level onto the kerb face with a level and mark a line; then photograph each run with a rule from that line up to the top, and file the photos by chainage. Check the top line with a string line at the start and at the end of every run, and look along it in between. On the concealed-works sheet, do not leave the embedment box blank for someone to fill in later: print it as “section height − measured exposure − bed”, and let the inspector enter readings only. Once the backfill is compacted the exposed height is fixed, and the only way to change it is to lift the stone.