How Long Is Granite Production Lead Time? Four Stages, Not One Number

Granite production lead time is not one number. It is four stages added together: drawing stock, sawing, surface finishing and packing. Three suppliers can give three figures for the same order, because they start counting on different days and sit in different queues. This article gives the parallel-or-queue table, the three confirmations that start the clock, and four questions to ask. Our 5-day dispatch applies to stock sizes only.

How long is granite production lead time, and why is there no single figure?

There is no single figure, because lead time is four stages added together: drawing stock, sawing to size, surface finishing and packing. For one batch of slabs these stages run in series. The next machine cannot start until the previous one releases the stone. Overlap happens in two places: sending different sizes to different machines, and, inside surface finishing, running edge work and flaming on separate equipment (the two rows in the section-four table). That is why the same order changes duration when the specification changes. Our 5-day figure is reserved for stock sizes: Maple Red G562 (old code G4562, also sold as Cenxi Red), 30mm polished, already in the yard as the same batch, where the work is counting, re-checking and packing. Cut-to-size, special shapes and multi-edge work cannot use that figure and are re-sequenced through the shop. Our 20 saws and 500,000 m² a year describe capacity, not a promise attached to one order.

Why do three suppliers quote three different lead times for the same order?

Because they count from different days. Three starting points are common: the quotation date, the day the deposit lands, and the day the drawings are approved. Between a quotation and a deposit there may be days of your own approval process, and whether those days sit inside the supplier's figure depends on which start he chose. The second variable is invisible: the production queue. The same sentence — "we start when the deposit arrives" — can still land on very different dates depending on how many orders sit ahead of yours. Neither can be guessed, so ask. One action is enough: ask which day the count begins, and have that start written on the quotation. Put the clocks on the same footing before you compare: if a supplier counts from the deposit, ask whether drawing approval and the sealed colour can be completed ahead of it. If they cannot, add that gap to his figure before comparing.

Where does the extra time in cut-to-size work actually go?

Into the two stages that follow sawing: surface finishing and packing. Sawing cuts slabs to finished size, and on 30mm material every cut removes a kerf, so the nesting has to absorb the kerf before the first pass; get it wrong and the layout is redone. Surface finishing splits into two lines. The face is polished or flamed; the edge is ground or chamfered. Each line has its own machine and tooling, so one profile means one set-up, and a change of profile means changing, dressing and testing the wheel. Which line goes first depends on the face: on flamed slabs the edge is usually worked after burning, because an edge ground first tends to chip where the flame passes. Packing closes the job, and that is where crate or bundle and corner protection are fixed. Every extra profile and every extra size adds one more set-up and one more tool change. Special shapes — cut-outs, curves, patterns — do not run on this line and are scheduled on a separate sheet. So to quote days for cut-to-size work, first count how many sizes and how many edge profiles the order contains. The table in section four splits edge work and flaming into two rows because they occupy different equipment, not because there are two more stages.

Which jobs can run at the same time, and which have to queue?

One test covers it: do the two jobs compete for the same machine or the same slab. Same slab means they queue. Same machine means they queue. Neither, and they can overlap. Applied to your order: stock release waits for colour approval and the deposit; sawing waits for approved drawings and released slabs; edge work and flaming both wait for sawing; packing waits for finished surfaces and shipping marks. Different sizes on different machines can overlap; the same holds for edge work and flaming when they sit on separate equipment. So when a buyer asks for a shorter lead time, the real question is which stage can be pulled out and run in parallel.

StageWhat must be finished firstCan it run alongside other work?
Drawing slabs from stockColour reference sealed, deposit received, same batch in stockNo with sawing on this order; yes with stock release for other orders
Sawing to sizeDimension drawing approved, kerf and nesting calculated, slabs releasedYes with sawing for other sizes on other saws; no with edge work on the same slabs
Edge work and chamferBatch sawn, profile and allowance confirmedDifferent slabs can run in parallel; on the same slab finish the face first (polished or flamed), then the edge; no with packing
Flamed finishSawing finished, surface cleaned before burningDifferent slabs can run in parallel; on the same slab flame first, then edge; no with packing
Packing and shipping marksSurfaces finished, marks and packing data receivedYes with booking and the loading plan; no with the earlier stages of this order

Which day should the clock start, so the wait is not wasted?

Day zero is the day three confirmations are complete: approved dimension drawings covering edge profile, cut-outs and joint direction; a sealed colour reference; and the deposit in the account. With one missing, sawing has no basis to start: an open drawing cannot be cut and then undone; an unsealed colour can produce a batch of off-shade slabs that no buyer will accept; an unpaid deposit keeps the slabs on the stock ledger, with no bay allocated. These three are written on the order confirmation form at our own plant, and you can carry that form to other suppliers and ask them the same question. Two more documents do not hold up sawing, but have to be complete before packing: shipping marks, front and side, and packing instructions covering crate or bundle, pieces per box and corner protection. Late on these does not stop the saw; it stops the packing stage — sawn slabs stand in the shop waiting for paperwork, and the goods do not leave. So write the start of the contractual lead time as the day the three confirmations are complete, not the signature date.

What should I ask at quotation stage to get a real lead time?

Once day zero has a definition, ask four questions, in this order. Which day does the count start. How many days for stock release, sawing, surface finishing and packing, each on its own. Which of the four is the constraint, and is it the machine or the material. Whether the order can ship in parts. Four answers leave you with a stage-by-stage schedule instead of one total. Split shipments by completion order, not by halving the area. Cut-to-size pieces are crated upright, so the container carries boxes rather than square metres: have the forwarder load-plan the sizes that are already finished, ship what fits and hold the rest for the next batch. The 346 m² per 20ft container figure holds only for stock slabs loaded flat, so do not divide a cut-to-size area by it to work out container count. Then put the schedule in the contract: start date, days per stage, and what happens if a stage runs over. A contract that carries one total figure and no start date leaves you nothing to reconcile when a dispute arises.