Granite Slab Numbering for Installation: Three Documents and a Three-Part Code

Granite slab numbering for installation rests on three documents: a measurement sheet, a layout drawing and a cutting list. One code, built from elevation, row and column, has to run through all three, or the wall goes up mirrored. A 20ft container holds 346 m², about 961 slabs at 600×600; with no number on the crate, unloading means opening every crate.

How many documents does a layout and numbering package actually need?

Granite slab numbering for installation needs three: a measurement sheet, a layout drawing and a cutting list. The measurement sheet records the net size and squareness of every face and carries numbers only, no approximations. The layout drawing fixes which slab goes where, with its number, vein direction and viewing direction. The cutting list follows the numbers and gives each slab its finished size, edge profile and surface, and the workshop cuts from that list. Each does one job and none replaces another. Merge them into one sheet and every size change has to be made in three places, and the place you miss is the one nobody catches. Set the three side by side and one conclusion follows: the number is the only thing they share, and once it breaks the three become three unrelated sheets of paper. That number is the single field running through all three documents, and the six sections below are about how to set it and how to land it on the crate.

DocumentWhat it controlsWhat happens without it
Measurement sheetNet size and squareness of each face, smallest reading usedCut to drawing sizes and a whole run along the wall will not fit
Layout drawingWhich slab goes where: number, vein direction, viewing directionNo fixed position on site and the fixer guesses
Cutting listFinished size, edge profile and surface for each numberWorkshop falls back to defaults and edges and surface come out wrong

Why can't the layout be drawn straight off the architectural drawing?

Because the architectural drawing gives design dimensions, while the site is the finished face after plaster, levelling and waterproofing. The gap between the two is not constant, and it varies from point to point on the same wall. So measure every wall at top, middle and bottom, and at left, centre and right within each of those, then take the smallest reading as the net width. On floors measure the four edges plus both diagonals; unequal diagonals mean the shape is not square, so lay it out as the quadrilateral you actually have. The edge course along the wall will then hold tapered pieces, and both the wide end and the narrow end of each piece must be marked on the drawing. The smallest reading is the one that fits; the surplus is taken off at the closing edge. All of the difference must land on the closing edge, the edge course along the wall or against the door casing. Land it in the middle and you get a diagonal joint, with neither side matching and no trim wide enough to cover it.

How should the code be built so a fixer can find that slab on site?

Three segments: elevation, row, column, written as A2-03-05. The elevation matches the plan. Rows count up from the finished floor, with the first full row as 01. Columns count from a datum corner to the far end, and the datum corner goes into the legend. With all three in place a slab has one position in the building, never two. Read the three together and there is one conclusion: drop the column segment and nothing blocks the mirror, because elevation and row cannot tell left from right. Never write the column as left to right, because turn around and left becomes right. The starting point has to be something you can touch on site: the internal corner on the door side, or the corner that matches the lower left of the drawing.

SegmentWhat it carriesWhat goes wrong
ElevationThe wall it belongs to, matching the plan, e.g. A2Two elevations sharing a code and nobody knows which wall
RowCounted up from the finished floor, first full row is 01Rows drift and the whole column sits at the wrong height
ColumnCounted from the datum corner to the far end, corner in the legendA mirror image cannot be told apart and slabs go up reversed

Is the drawing made looking from inside the room or from outside?

It has to state the viewing direction, because the same wall read from inside and from outside is reversed left to right. Put one line in the legend: view standing inside, facing this wall. Then draw at least one asymmetrical reference on that wall: a door opening, a column, a downpipe. A plain rectangle gives the eye nothing to fix left and right, and one reference is enough as long as it is unique to that wall. With no stated view the whole wall mirrors, the vein arrows flip with it, and the numbers look perfectly correct while every position is wrong. That error is invisible at drawing stage; it surfaces when the first slab is set, and by then the slabs are cut and rework is counted per piece.

Where do vein direction and face orientation go on the code?

Vein direction takes an arrow, and the arrow points to an absolute direction: up, or toward the door. Do not write "with the grain", because a vein has no arrow of its own and the note then says nothing. Vein direction is fixed at layout stage; once cut it cannot be changed, so one reversed arrow in the layout reverses the vein on the whole wall. Face orientation works the same way: the polished face goes outward, the back of the slab carries saw marks and mesh, and the number is written on the back, where it disappears after installation and never shows on the finished face. Define surface codes in the legend, P for polished and F for flamed, and do not use letters nobody defined. Where one wall mixes two surfaces the code must carry the letter, or the workshop runs the default on the whole wall and the split is discovered on site.

How does the number reach the crate so unloading doesn't mean unpacking everything?

The same set of numbers has to appear in three places: the drawing, the back of the slab, and the packing list, with the label on the outside of the crate counting as part of the packing list. Write the number in the same spot on every slab, top right of the back for instance, so nobody hunts for it. Label each crate with crate X of Y, containing A2-01-01 to A2-03-06. Keep one elevation per crate and do not mix elevations. A 20ft container holds 346 m², which at 600×600 is 346 divided by 0.36, about 961 slabs; mix them and finding one number means opening the whole container. Break any one of the three and the site is guessing, and the slab that gets guessed wrong will not meet its joint.

If one slab has to be replaced on site, can the numbers be re-issued?

No. Once the numbers leave the factory they are the only index for that batch: re-issue them and the slab backs, the crate labels and the cutting records all become void at the same moment, and nobody can tell which sheet belongs to which slab. A replacement takes a suffix, the original number plus -B, and the variation order says replaces original. A revised drawing carries a revision number and a date, the old revision is withdrawn, and the workshop works only from the latest. Put the rule in the order rather than in an email: at Guangxi Shicai Stone Industry Co., Ltd. cut-to-size orders for Maple Red G562 in 30mm start at 100 m² with 5 days to ship, so the numbering and the revision should be fixed when the order is placed, and only that version counts afterwards.