Protecting Granite During Construction: Three Stages, Not One Sheet of Plastic
Protecting granite during construction is not one sheet of plastic at the end. It runs in three stages: setting down, installation, and finished to handover. The requirements conflict, since impact protection wants something hard and dirt protection wants air. A 30mm slab weighs about 81 kg per m², and a stack over the middle of a slab starts the crack.
How should granite be protected during construction, and where do you start?
Decide which stages need protection and how long each lasts. Then buy materials. A site has three stages: setting down, when slabs are unloaded and stacked; installation, when people walk on the stone and other trades work around it; and finished to handover, when the stone is covered and later uncovered. The three pull in different directions. Setting down needs slabs on edge, face to back. Installation needs impact and splash protection. The finished stage needs dirt kept off and air kept moving. One material used from start to finish gets at least one stage wrong. Three actions: check the crate is still square and the slabs still on edge when they arrive; confirm the bedding has hardened before anyone walks on it; confirm no standing water sits on the face or in the joints before you cover. A chip the size of a peanut on an outside corner usually means one of the first two was skipped: a crate levered apart, or traffic on bedding that had not set. Why setting down needs machinery comes down to the weight of the crate: the Maple Red G562 we supply (G4562, from our own quarry in Cenxi) is normally 30mm polished; a 20ft container takes 346 m², which at 81 kg per m² comes to 28 tonnes, with a 100 m² minimum. A load that heavy cannot be held by hand once a crate lets go, so setting down means a forklift and slings, not people lifting.
How soon can people walk on new paving, and can you stack material on it?
Skip the day count and use three checks you can run on site. Stand on it: the slab should not sink. Tap the corner and the middle: the sound should be solid, not hollow. Press the mortar that squeezed out at the edge: it should not give under a fingernail. All three pass, and people can walk. Stacking is a separate rule. Load goes over the supports, never over the middle of a slab. A 30mm slab weighs about 81 kg per square metre (0.03 m × 2.7 t/m³). Three 1 m² slabs stacked in one place come to 243 kg. On site the slabs are usually 600×600: one is 0.36 m² and about 29 kg, so ten of them make 290 kg. Load over the middle turns that stretch of slab into a beam. Bedding is never a hundred percent in contact; every low spot leaves a void, and that stretch of slab bridges it with nothing underneath. That is where a crack starts. Stack one layer only, on a full sheet or a continuous timber bearer, and keep the stack against a wall or edge, not in the middle of a walkway.
What should you cover granite with, and what should never go straight on it?
Buy two kinds of material: one against impact, one against dirt. Impact protection needs a hard board over a soft layer. A hard board straight on a polished face turns one grain of sand into a patch of haze. Dirt protection needs a peelable film or a tarpaulin, weighted at the lap and never sealed at the edge: lap the sheets by a hand's width, hold them down with sandbags or bricks, and leave a palm-sized opening at each corner for air. The weights stop wind and dust; the lap and the openings let vapour out. Condensation under the sheet, or a face that has gone darker, means it is not breathing, so lift an edge that day. Seal the edges and the moisture from the slab and the bedding has nowhere to go; it sits on the face as a water mark or efflorescence. Adhesive film suits a polished face for a short period only. Flamed and bush-hammered faces are rough, the adhesive does not hold, and residue stays in the pores, where it is harder to remove than the original dirt. Do not apply adhesive film where the sun hits all day; the adhesive transfers to the face.
| Material | What it stops | Where it belongs | How not to use it |
|---|---|---|---|
| Plasterboard or 9mm ply over non-woven | Falling objects, impact | Walkways and material routes | Hard board straight on a polished face, no soft layer |
| Low-tack peelable film | Mortar and paint splashes | Finished walls and worktops, short term | Left on through a full day of sun, adhesive transfers |
| Tarpaulin | Rain and dust from above | Open storage, temporary hoarding | Tied shut on all four sides, trapping moisture |
| Timber bearers | Keeps slabs on edge, puts load on supports | Unloading and site storage | Placed under the middle of a slab, off the supports |
Which trades on a shared site damage finished granite?
Four, in the order they usually appear. Welding and cutting: sparks pit a polished face and grinding dust lodges in the pores. Paint and render: spatter wipes off while wet; once dry, soften it with a poultice and scrape it off, and grind only where a thick film such as texture coating will not soften. Scaffolding and steel tube: a dropped standard chips the outside corner, and the chip starts at the arris. Drilling and chasing: an anchor set too close to an edge splits it when tightened. Four matching actions: lay a fire blanket over the welding zone and a second layer over the stone; mask the stone in bays with sheet and tape before spraying, with tape on the joint line only and never across the middle of a face; put timber under scaffold standards and soft caps on tube ends; keep the hole at least two diameters in from the edge — for a 10mm anchor, no closer than 20mm — so there is stone around the expansion; that is site practice, and the anchor maker’s edge distance still governs. If the layout will not allow it, switch to an undercut anchor or move the hole towards the middle rather than forcing it. Drill the first hole in an offcut from the same batch and tighten it; if the edge holds, repeat across the face.
Mortar, paint and adhesive have landed on the stone. How do you tell a stain from damage?
First decide whether the mark sits on the surface or inside the pores. On a polished face most marks stay on the surface and lift with a wet cloth and a plastic scraper. On flamed and bush-hammered faces the dirt goes into the pores, so it needs a wet poultice left to soften, then a brush worked along the texture. The order is fixed: soften, work it mechanically, and use chemistry last. Acid washing is the final step, not the first. Acid kills the polish and blotches dark stone. Test any cleaner on an edge or a spare slab, let it dry, and check for a colour difference before you touch the main area. Rinse with clean water and dry it off. Cleaner left in the joints comes back as a line a few days later.
| Stain | Do this first | Do not |
|---|---|---|
| Cement slurry, mortar | Soften with a wet poultice, push with a plastic scraper, rinse | Acid or a wire brush |
| Paint, coating | Wipe with the matching thinner while wet; once dry, soften then scrape | Flood the area with thinner so it runs into the joints |
| Adhesive residue from film | Warm with air, then roll it up in one direction | Lift it with a blade and cut scratches into the face |
| Rust and yellow marks | Find the water source, stop it, then treat the spot | Brush on rust remover and leave it |
Before handover, in what order do you uncover and inspect?
The order is photograph, uncover in zones, then six checks. Photograph the whole face and the details for the record. Then work from the inside out, one zone at a time, checking each zone as you open it; do not strip the lot at once. The six: chips on edges and corners; scratches, viewed across a polished face at a low angle; colour variation, against a spare slab from the same batch; hollow spots, by tapping every slab; water marks and efflorescence, read after the stone has dried; and joint width against step. When something turns up, do not reach for the grinder first. Grinding fixes scratches only; hollow bedding and efflorescence survive it, and the cause sits back in the work sequence. Leave one spare slab from the batch on site, or you have nothing to match a repair against. Take the sheeting and adhesive residue away the same day, not after handover.