Granite slab storage on site: chalk one bay per crate before the truck arrives

Granite slab storage on site is a layout problem, not a list of cautions. Take the packing list, chalk one bay per crate, land by crate number, keep the timber frame on, stand the slabs up, then check bundle weight against the floor. A 20 ft container holds 346 m² — about 961 pieces at 600×600, roughly 28 t — and one bay in the wrong place makes every bundle behind it move twice.

What comes first on site, unloading or marking the bays?

Mark the bays first, then let the truck in. Once it stops, slabs come off and, with nowhere to go, lie flat on the ground for days — the one position you least want. Take the packing list before delivery, chalk one bay per crate, and write three things on each: crate number, the numbering block inside, and the order it will be opened. Leave the timber frame on. It is not packaging; it is what holds the bundle upright — two uprights clamp the stack, the base spreads load onto the bearers. Strip it and the slabs have nothing to lean on. The forklift goes under the base, never into the side. Leave two lanes, one for the forklift and one for people, sized to the turning circle on your site rather than copied from another project. Photograph the finished layout and post a copy at the gate and in the site office.

Should the slabs stand up or lie flat once they arrive?

Stand them up. Flat is for short transfers only. Granite is strong in compression and weak in bending, and a 30 mm slab already weighs 81 kg per square metre from its own mass. Lying flat, that mass is spread over the whole panel, but a 30 mm slab cannot carry the bending moment: supported at two ends and spanning in the middle, the underside cracks in tension first; any high point underneath then becomes a concentrated load, and the crack starts there. You will not see it at ground level; it shows at an edge after the panel is on the wall. If a slab has to lie flat, three conditions together: single layer, nothing stacked on top, continuous dunnage underneath instead of two bearers with air between. Keep it to the window between unloading and racking. Standing, face to face with a soft gasket between, polished surfaces inward, so the visible face is never rubbed against the frame. Leave a gap between panels: pressed tight, taking one out disturbs the whole bundle.

How heavy is one bundle, and will the floor take it?

Work out the bundle weight before choosing the spot. At 2.7 t/m³, a piece weighs area × thickness × density. Forty pieces per bundle is an example only — ask the supplier for the real figure. The table is the input; the floor is the question. Look at the two rows at 48.6 kg: same weight, different footprint, so the pressure per square metre differs. For a standing bundle the bearing area is the footprint of the timber base, not the slab face; report the bundle weight and that footprint together to the structural engineer. The heaviest bundle in the table is 3.24 t; spread over four bearers that is about 810 kg per bearer. Bearers run the full length of the bundle, not short blocks at intervals. Never stand a bundle over backfill, a pour strip or a service trench cover; if the slab is not ground-bearing, ask the structural engineer.

Size (mm)Area per pieceWeight per piece40 pieces, approx.
600×600×300.36 m²approx. 29 kgapprox. 1.16 t
600×600×500.36 m²approx. 48.6 kgapprox. 1.94 t
1000×600×300.6 m²approx. 48.6 kgapprox. 1.94 t
1000×600×500.6 m²approx. 81 kgapprox. 3.24 t

What keeps a standing bundle from going over?

Three things: a rack, a bottom stop, and soft packing. Use an A-frame or a proprietary slab rack, with the stack close to vertical and leaning slightly back — an experience value, not a standard; the actual angle comes from the rack maker. The more the stack leans, the more of its weight goes into the rack, so size the rack for the whole bundle. The closer to vertical, the more the weight sits on that 30 mm base edge, and if the stop block and floor friction cannot hold it, the stack slides forward. At the base, a stop block catches the bottom slab and prevents the whole bundle sliding forward. A rack alone holds the back; the front still runs away. Soft gaskets between slab and slab and between slab and rack do two jobs: protect the polish and add friction. Three things not to lean on: a wall, which wicks damp and was not designed for your load; a column, whose face is rarely flat, so force lands on one point; and scaffolding, which is temporary and has people working on it. Toppling starts as a slide at the base, so fit the stop before the rack.

Open yard or a covered shed?

Hard standing with a drainage fall comes before a shed. Hard standing means concrete or compacted crushed stone, not gravel tipped over backfill. The fall takes water away so the base of the bundle never sits in a puddle. In the open, roof it only: cover the top, leave the sides open to move air, don't wrap the whole bundle. Keep the bottom off the ground on bearers or blocks so damp cannot rise. For storage that crosses a wet season, check two more things: whether the mesh on the back is lifting or de-bonding, and whether rust spots have appeared on the back. Read the pattern first: rust in a row along the mesh staples or the binding wire is external iron; scattered spots that follow the veining are more likely iron minerals in the stone itself, which do not wipe off. Pull those slabs out and keep them away from the batch going on the wall. A shed is optional — the roof and the fall are the part that works; a shed over a floor that does not drain is as damp as the open yard. Protecting the stone after it is fixed is a separate job — see the guide linked below.

Which bundle do you open first?

Work backwards from the installation sequence. The setting-out drawing decides which elevation goes up first; the bay nearest the access lane holds that elevation's numbering block, and the deepest bay holds the last. The bay tag carries the crate number plus the numbering block inside, so whoever collects a bundle picks correctly without reading the drawing. The cost of a wrong stack is easy to state: a 20 ft container holds 346 m², about 961 pieces at 600×600, roughly 28 t. At an assumed 40 pieces per bundle — ask the supplier for the real figure — that is just over 24 bundles. If the first-fixed bundle sits behind the last, all 24 move. Spares and offcuts get their own bay, never mixed with waiting stock, or finding one replacement means opening everything. Before handing the area to the fixing crew, walk the bays in order: frame intact, no lean, bearers not crushed, stop blocks still in place, no rust on the backs, crate labels still legible.